A project is showed as follows a Find out the critical path

A project is showed as follows: (a) Find out the critical path of the Project (b) Fin out the duration of the projcet (c) Find out the slack time for each activity

Solution

a) critical path:

1. A-D-G = 8+5+7 =20 days

2. A-E-I =8+1+9 =18 days

3. B-I = 4+9 =13 days

4. C-F-I = 3+2+9 = 14 days

5. C-H-J = 3+6+9= 18 days

Critical path = A-D-G being the longest

b. Duration = 20 days (duration of the critical path)

c. Slack time:

Task Name Duration
(exp. time)
ES EF LS LF Slack
Start 0.00 0.00 0.00 0.00 0.00 0.00
Task A 8.00 0.00 8.00 0.00 8.00 0.00
Task B 4.00 0.00 4.00 7.00 11.00 7.00
Task C 3.00 0.00 3.00 5.00 8.00 5.00
Task D 5.00 8.00 13.00 8.00 13.00 0.00
Task E 1.00 8.00 9.00 10.00 11.00 2.00
Task F 2.00 3.00 5.00 9.00 11.00 6.00
Task G 7.00 13.00 20.00 13.00 20.00 0.00
Task H 6.00 3.00 9.00 8.00 14.00 5.00
Task I 9.00 9.00 18.00 11.00 20.00 2.00
Task J 6.00 9.00 15.00 14.00 20.00 5.00
Finish 0.00 20.00 20.00 20.00 20.00 0.00

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site